MAIN STREET PROJECT

  • March 1, 2021 – Move Into Field Office
  • March 4-6, 2021 – Engineering/Layout
  • March 8, 2021 – Signs and Maintenance of Traffic
  • March 9 & 10, 2021 – Removal of Trees and Clearing
  • May 28 – Phase 3 begins
  • June 15, 2021 – Curbing and bumpouts formed
  • August 20, 2021 – Street was milled and paved, sidewalk benches, trash cans, and bike racks set
  • August 20, 2021 – Railroad crossing reconstructed
  • November 1, 2021 – Bumpouts landscaped
  • November 2021 – Trees planted
  • February 2022 – Street lamp posts erected

 